Hi all,
Hopefully a simple query - in the main Overview screen, Network appears in the Opex chart.
However, when you goto edit the Network costs by NIC type (eg 1Gb or 10Gb) this would be a Capex cost (eg if you do a cost per port).
The Labor section also doesn't allow for Network labour.
How are people handling this ? Do you bundle the labour (eg network team salary, % time spent on data-centre networking) into the per NIC cost to get it included.
Thanks in advance,
Raj.